Studi Penjadwalan Pelaksanaan Konstruksi Main Dam Pada Bendungan Cijurey Kabupaten Bogor Provinsi Jawa Barat

Authors

  • Andry Sofyan Arissaputra
  • Suwanto Marsudi
  • Evi Nur Cahya

DOI:

https://doi.org/10.21776/ub.jtresda.2023.003.01.25

Keywords:

Scheduling, Cost, Working Hours, Heavy Equipment

Abstract

Good project management is essential for resource planning and procurement and scheduling of the project itself. The purpose of writing this study is to optimize time, resources, and tools with the most optimal project costs for the construction of the Cijurey Dam Main Dam using the program. The alternative is to increase the duration of working hours and the number of heavy equipment. The problem is analyzed by evaluating the work schedule, with alternatives to solving the acceleration of the project by optimizing the work on the addition of heavy equipment and working hours which will ultimately have an impact on the required cost budget. From the analysis results obtained, the project's normal duration is 687 days. The optimal result of the scheduling alternative was the addition of the duration of working hours with a decrease in the cost budget plan by 0.69% and an acceleration in duration by 22.27%.

Manajemen proyek yang baik sangat penting untuk perencanaan dan pengadaan sumber daya dan penjadwalan proyek itu sendiri. Tujuan penulisan studi ini adalah untuk melakukan optimasi waktu, sumber daya dan alat dengan biaya proyek yang paling optimal pada pembangunan Main Dam Bendungan Cijurey dengan menggunakan program. Alternatif yang digunakan adalah dengan menambah durasi jam kerja dan menambah jumlah alat berat.Permasalahan dianalisa dengan mengevaluasi jadwal pekerjaan, dengan alternatif pemecahan percepatan proyek dengan optimalisasi pekerjaan pada penambahan alat berat dan jam kerja yang pada akhirnya akan berdampak pada anggaran biaya yang diperlukan. Dari hasil Analisa didapatkan, durasi normal proyek selama 687 hari. Hasil optimal dari alternatif penjadwalan adalah penambahan durasi jam kerja dengan penurunan rencana anggaran biaya sebesar 0,69% dan mengalami percepatan durasi sebesar 22,27%.

References

Husen, A. Manajemen Proyek Edisi Revisi. Yogyakarta: CV. Andi Offset, 2010

Nurhayati, Manajemen Proyek Edisi Revisi. Yogyakarto: Graha Ilmu, 2010

Ali, Tubagus Haedar. Prinsip-primsip Network Planning. Jakarta: Gramedia, 1995

Rizal , Rizal. “Studi Manajemen Konstruksi Proyek Rehabilitasi Bendungan Simo di

Kabupaten Grobogan dengan Menggunakan Program Microsoft project Manager 2016†Jurnal

Teknologi dan Rekayasa Sumber Daya Air. Vol.2 No.1, 2022

Widiasanti, Irika & Lenggogeni. Manajemen Konstruksi. Bandung: Remaja Rosdakarya Offset,

Neditia, Dwandika V et.al. “Studi Perencanaan Jadwal Pelaksanaan Konstruksi Main Dam dan

Bangunan Pelimpah (Spillway) Pada Bendungan Gondang Kabupaten Karanganyar Provinsi

Jawa Tengah Dengan Menggunakan Microsoft Project Manager 2016†Jurnal Mahasiswa

Jurusan Teknik Pengairan. Vol.2 No.2, 2019

Alfredo. Moch et.al. “Studi Manajemen Proyek Bendungan Beton Di Kualu Kabupaten

Tobasamosir Dengan Menggunakan Microsoft Project 2013†Jurnal Mahasiswa Jurusan Teknik

Pengairan. Vol.2 No.1, 2018

Ervianto, Wulfram I. Manajemen Proyek Konstruksi. Yogyakarta: CV. Andi Offset, 2002

Soeharto, Imam. Manajemen Proyek Jilid I. Jakarta: Erlangga, 1999

Downloads

Published

21-10-2022

How to Cite

Arissaputra, A. S., Marsudi, S., & Cahya, E. N. (2022). Studi Penjadwalan Pelaksanaan Konstruksi Main Dam Pada Bendungan Cijurey Kabupaten Bogor Provinsi Jawa Barat. Jurnal Teknologi Dan Rekayasa Sumber Daya Air, 3(1), 288–297. https://doi.org/10.21776/ub.jtresda.2023.003.01.25